Procedures of Application for Industrial Park Establishment (With an Applied Area of 30 Hectares or Under)

Industrial Innovation Act was announcement on 12 May, 2010. In regards to the establishment of industrial park, the major transformation is focused on the change of park type and the simplified establishment procedures.
Industrial Innovation Act offers more diversity in the park, hence the establishment of other types of parks such as culture and creativity, logistics, telecommunications and media, etc., which speeds up the development of versatile diverse industries. The procedures of application have also been greatly simplified. For example, industrial parks with an area of 30 hectares or under can now be examined and approved by county/city governments accordingly, which largely decreases the processing time of each case.

  • Industrial zone application and establishment flow chart, please refer to the text description below for details.

    Detailed description below the picture:
    This flow chart shows the application process for setting up an industrial zone with an area of ​​less than 30 hectares. The main steps are as follows:
     1. Survey: The applicant submits land survey information, and the Economic Development Bureau of the Tainan City Government organizes the survey and integrates the opinions of relevant units.
     2. Preliminary review: The applicant makes corrections based on the consultation opinions and submits a feasibility planning report, urban plan, development plan and environmental impact assessment materials. The Economic Development Bureau will check the completeness of the information and review it together with relevant units.
     3. Review: Depending on whether the application requires an environmental impact assessment (non-urban land of more than 10 hectares, urban land of more than 5 hectares):
     • Environmental impact assessment required: Send the environmental impact assessment report to the Tainan City Government Environmental Protection Bureau for review.
     • No environmental impact assessment is required:
     • Urban land: sent to the Ministry of the Interior for review of urban plans.
     • Non-urban land: Send to Tainan City Government Urban Development Bureau for review of development plan.
    Subsequently, all cases were submitted to the "Tainan City Government Industrial Park Establishment Review Group" for review.
     4. Approval Announcement: After the establishment is approved by the Tainan City Government, it will be announced and reported to the Ministry of Economic Affairs for review.

Explanations of Application Flowchart:

Step 1: Joint Site Investigation
Applicant (check land selection information) → Economic Development Bureau, Tainan City Government (carry out joint site investigation and collect opinions from related organizations)

Step 2: Initial Review
Applicant (adjust and check related documents accordingly based on the opinions gathered from the joint site investigation - feasibility report / urban planning and development planning / environmental evaluation) → Ministry of Economic Affairs, R.O.C. (check if all documents have been prepared, and meet up with relevant organization)

Step 3: Examination
Is environmental evaluation required? (Non-urban Land: over 10 hectares) (Urban Land: over 5 hectares)
YES→ Submit to the Ministry of Economic Affairs, R.O.C. for examination (examine environmental evaluation)
NO→Urban land: Submit to the Ministry of the Interior (examine urban planning); Non-urban land: Submit to the Bureau of Urban Development, Tainan City Government (review development planning)

Once completed, submit them all to the “Discussion Group of Tainan City Government Industrial Park” (discuss about the application of industrial park establishment)

Step 4: Approval and Public Announcement

Submit to Tainan City Government, and they will approve and publicly announce the establishment, then notify the Ministry of Economic Affairs, R.O.C. for future reference.

Step 1: Joint Site Investigation
Applicant (check land selection information) → Economic Development Bureau, Tainan City Government (carry out joint site investigation and collect opinions from related organizations)

Step 2: Initial Review
Applicant (adjust and check related documents accordingly based on the opinions gathered from the joint site investigation - feasibility report / urban planning and development planning / environmental evaluation) → Ministry of Economic Affairs, R.O.C. (check if all documents have been prepared, and meet up with relevant organization)

Step 3: Examination
Is environmental evaluation required? (Non-urban Land: over 10 hectares) (Urban Land: over 5 hectares)
YES→ Submit to the Ministry of Economic Affairs, R.O.C. for examination (examine environmental evaluation)
NO→Urban land: Submit to the Ministry of the Interior (examine urban planning); Non-urban land: Submit to the Bureau of Urban Development, Tainan City Government (review development planning)

Once completed, submit them all to the “Discussion Group of Tainan City Government Industrial Park” (discuss about the application of industrial park establishment)

Step 4: Approval and Public Announcement

Submit to Tainan City Government, and they will approve and publicly announce the establishment, then notify the Ministry of Economic Affairs, R.O.C. for future reference.